Shop (Main Floor) + The Roost — Turkey Toe Saloon Social Club (Upper Level). Built for hard-bid, trade selection, and phasing. Read alongside the construction documents and issued CDs — not in place of them.
Stop — Resolve Before Fabrication or Trenching
Critical Issues Identified in MEP Review
These are not formatting notes. They are structural, code, and coordination gaps that, if unresolved, will cause either a failed inspection, an unsafe building, or work that has to be torn out. Each one needs a decision before Caldwell trenches or Huron fabricates.
Outdoor kitchen + Chimney 2 have no roof
A grease-rated hood duct must terminate through a roof. Chimney 2's double-sided firebox sits between Buildings A and B — two independent structures with no shared roof. There is currently no documented structure covering this space. This sounds like an undocumented third structure (breezeway, pavilion, or covered outdoor room) that needs its own design, CDs, and foundation before Caldwell's site work locks in. Resolve this before any trenching.
→ Design decision + Eric's CDs — before Caldwell mobilizes
Chimney 1 — one flue serving two fireboxes on two floors is likely not code-legal
Solid-fuel fireplaces each require their own dedicated flue. A see-through fireplace (one firebox, two openings at the same level) is legal and common. Two separate fireboxes on two different floors sharing one flue is a different thing and almost certainly fails code. Get a mason or mechanical engineer to confirm before this goes into flat-pack fabrication — you cannot fix the flue after framing is complete.
→ Mason / mechanical engineer sign-off — before flat-pack fabrication (Huron)
400 CFM range hood likely triggers make-up air requirement
Most jurisdictions require mechanical make-up air when exhaust exceeds 400 CFM (IMC 504.5 / IRC M1503.6). Nothing in this MEP addresses make-up air. If required, it's a dedicated duct system, a damper, and possibly a tempering unit — not a minor add. Confirm with AHJ before mechanical scope is bid.
→ AHJ confirmation — before mechanical bid
Full cooking equipment may trigger commercial kitchen code
A full fridge + double oven + 400 CFM grease hood is real cooking, not a prep kitchen. Depending on jurisdiction and event/catering use, this may require: (1) NFPA 96 fire suppression (Ansul system) over the hood, (2) grease interceptor on the kitchen sink and dishwasher drains (not just the wash-down bay), (3) health department permit for event catering. Have a direct AHJ conversation before this scope is priced — these are not small adds.
→ AHJ + health department — before kitchen scope is finalized
Wood-burning fireplace circuits show 'blower/igniter' — contradiction
Igniters are a gas fireplace feature. True wood-burning fireboxes have no igniter — at most a circulation blower. If there is an igniter, that implies a gas line, which conflicts with the all-electric assumption throughout this document. Confirm with the fireplace sub: are these true wood-burning? If so, remove 'igniter' from the circuit description and confirm whether a circulation blower is actually planned. If gas is introduced anywhere, the all-electric MEP narrative needs revision.
→ Fireplace sub confirmation — before Panel A/B schedules are issued for bid
Occupancy classification — shop by day, event venue by night
A building that functions as an equipment storage shop and converts to an event venue changes occupancy classification at use. This affects emergency lighting extent (may need to cover the main floor and Roost, not just the stairwell), exit signage, occupant load calculation, and door hardware. Confirm with AHJ before electrical rough-in — egress lighting placement is locked in early.
→ AHJ occupancy classification — before electrical rough-in
Spark arrestors + wildfire requirements — two wood-burning chimneys in a mountain setting
Wood-burning chimneys in forested/mountain settings often face local fire authority requirements beyond standard AHJ — spark arrestors, ember-resistant design, setback from combustibles. Westcliffe / Custer County fire authority may have specific requirements. Check with local fire authority separately from the building AHJ.
→ Local fire authority — before chimney masonry sub is hired
Panel A is likely over 42 spaces — may need a 60-space can
Circuit numbering has drifted (A21b, A21c, A35–A38, A39–A46). Every 240V/2-pole breaker takes 2 slots. Double oven (50A/2P), outdoor appliance (30A/2P), compressor (30A/2P), welder (50A/2P), water heater (30A/2P), UTV charger (50A/2P), mini-split (20A/2P), fireplace circuits, outdoor chimney circuits — that's 14+ slots from 2-pole breakers alone before any 1-pole circuits. Recount actual slot usage before Panel A goes out to bid. May need a 60-space can.
→ Electrician load calc — before Panel A equipment is ordered
Range/oven vs. double oven — cooktop missing if they're separate
The zone table says 'range/oven (dedicated 240V).' The open decisions and panel schedule say 'double oven.' A double wall oven has no cooktop. If there's also a cooktop (range top), that's a separate dedicated 240V circuit not currently in Panel A. Decide: double oven only, or double oven + separate cooktop?
→ Appliance selection — before Panel A final schedule
Lumen Cache lag — universal rough-in fallback needed
Framing locks the chase and duct paths (Build Sequence Step 3). If Lumen Cache's design isn't complete before framing, conduit paths won't be coordinated. Add a universal rough-in standard now: extra empty conduit + pull string in all wall cavities and the chase, so walls don't get opened later. This is standard practice on CI-forward builds.
→ Add to framing spec — before framing begins
Outdoor kitchen electrical load on Panel A — confirm intentional
All outdoor kitchen circuits (A39–A46) are on Panel A, the Barn's panel. The outdoor kitchen is a shared amenity between Building A (House) and Building B (Barn). If Building A ever has its own panel or sub-panel, the outdoor kitchen's power source may need to move. Confirm this is intentional before rough-in.
→ Design decision — low cost to clarify now
P2 floor drain / grease interceptor — now includes kitchen sink and dishwasher
P2 originally asked about the wash-down bay floor drain. Given the cooking equipment now in scope, the AHJ may also require a grease interceptor on the kitchen sink and dishwasher drain — standard for commercial-adjacent kitchens. The P2 AHJ conversation needs to cover both.
→ AHJ — expand P2 question to include kitchen drains
Turkey Toe's caretaker zone is two separate, independently built structures — not one building. This document covers the Party Barn only.
Caretaker Building
Factory-built, two-box volumetric modular unit built offsite: Welcome Center side (guest check-in, full bed/bath) + Caretaker side (3 bed/2 bath, kitchen, living, decks). Factory-wired and plumbed. Excluded from this MEP scope except for confirming the factory package against final CDs.
Party Barn
Completely separate, site-built structure with its own foundation. Structural framing is flat-pack — fabricated offsite (Huron Components, from Eric's CDs) and assembled on site. Main floor: shop/equipment storage that converts to event venue. Upper level: The Roost (2,193 SF), home of the Turkey Toe Saloon Social Club.
Electrical
Site electrical service runs along State Highway 69 on a 13,864V/10kVA line feeding three transformers. A new transformer near the caretaker/shop zone provides split 200A service on independent panels. Inside the Party Barn: Panel A (main floor — shop lighting, cart charging, compressor, welder, bathroom/prep kitchen) and Panel B (The Roost — six zones each with dedicated circuits, simulator clean power, bar equipment, AV). Every exterior fixture is full-cutoff, downward-directed, warm-toned, and dark-sky compliant. Security lighting is low, ground-mounted — no pole fixtures.
Plumbing
Party Barn draws from the site's existing well/Norwesco tank system via a buried lateral, draining to the site septic system (Caldwell Family Concrete) via a buried sewer lateral. Main floor: full bathroom + prep kitchen on one vent stack. Upper level: Saloon bar sink drains down a 5'-5" vertical chase to the main-level stack; two powder rooms mid-floor. All exposed/exterior lines get heat tape and insulation — no option at 8,040 ft elevation.
Mechanical
All-electric, cold-climate mini-split heat pumps — no ducted forced-air, no gas anywhere. Main floor: one zone (bathroom/prep kitchen area). The Roost: two independent zones so the Saloon/simulator/game area and the fire lounge/fitness/balcony area condition independently. Exhaust: dedicated mechanical chase framed adjacent to bathrooms on the main floor — all exhaust systems (bathroom, powder rooms ×2, range hood, outdoor kitchen hood) run through or alongside this chase and terminate through the standing-seam metal roof with pre-flashed collars. Each system has its own dedicated duct and cap; no shared ducts, no horizontal runs (IMC 505). Wood-burning fireplaces: 2 chimneys, 5 fire positions. Chimney 1 runs through the barn interior — main floor event space firebox and Roost fire lounge firebox, one flue. Chimney 2 is outdoor between Building A and B — double-sided firebox at the main floor (both buildings face it) plus accessible from the Roost deck on the 2nd floor.
Coordination
Electrical trunk feed, water lateral, and sewer lateral all run from the same direction — bid and trench as one shared excavation scope through Caldwell/4K Services (already on site for septic). Open item: this document assumes trunk feed to house main panel, but the master-plan utility page describes independent 200A services off a dedicated transformer — reconcile with electrician before ordering service equipment.
| Zone | Electrical | Plumbing | Mechanical |
|---|---|---|---|
| Equipment / Cart Bays | Cart/equipment charging, storage lighting, bay-door openers, receptacles | None | None |
| Full Bathroom | GFCI recept., exhaust fan, lighting | Full fixture group — supply, waste, vent | Main-floor mini-split zone |
| Prep Kitchen | Small-appliance circuits, GFCI, dedicated dishwasher, full fridge (dedicated), range/oven (dedicated 240V), range hood (dedicated duct — straight out roof, independent termination), task lighting | Sink + dishwasher connection, fridge water line stub | Main-floor mini-split zone + dedicated range hood duct to roof |
| Covered Patio | GFCI recept., lighting, ceiling fan(s) | None | None |
| Outdoor Kitchen | GFCI recept., outdoor-rated appliance circuits, hood/exhaust fan, lighting | Outdoor sink, hot + cold supply, drain to sewer lateral | Ducted exhaust hood (shared Building A & B access) |
| Electrical / Mechanical Room | Main panels, network rack | Water entry, shutoffs, water heater | Indoor mini-split air handlers, condensate |
| Stairwell | Egress lighting w/ battery backup, 3-way switching | None | None |
| Zone | Electrical | Plumbing | Mechanical |
|---|---|---|---|
| Turkey Toe Saloon Social Club | Sim power/Cat6/low-glare lighting, bar equipment circuits, AV, general lighting/recept. | Bar sink + drain (chase to main-level stack) | Roost zone 1 |
| Indoor Putting Green | Accent/turf lighting | None | Roost zone 1 |
| Fire Lounge | Lighting, receptacles, wood-burning fireplace blower/igniter circuit (dedicated) | None — wood-burning, masonry chimney | Roost zone 2 |
| Game Area | Lighting, receptacles | None | Roost zone 1 |
| Fitness Zone + Upper Balcony | Lighting, receptacles (equipment-rated), balcony exterior lighting/GFCI | None | Roost zone 2 |
| Upper Powder Rooms (×2) | GFCI recept., exhaust fan, lighting — each room | 2× toilet + lavatory rough-in | Roost zone 2 |
Site Utility Layout — Shared Infrastructure → Building A (House) + Building B (Barn)
One transformer, one water lateral, one sewer — all split at the site before serving each building independently. Trench once, serve both.
SITE UTILITY ENTRY
══════════════════════════════════════════════════════════════════
[TRANSFORMER] ←── 13,864V / 10kVA line from State Hwy 69
│
│ 200A split service
├──────────────────────────────────────────────────────────
│ │
[PANEL A-MAIN] [PANEL B-MAIN]
Building A — House Building B — Barn
Caretaker Building Party Barn
(factory-wired, confirm Panel A (42-space, main floor)
against factory pkg) Panel B (30-space, The Roost)
│ │
│ shared trench ──────────────────────────────────────────│
└──────────────────────────────────────────────────────────┘
[WELL / NORWESCO TANK] ←── existing site water source
│
│ 1" water lateral (shared trench with electrical + sewer)
├──────────────────────────────────────────────────────────
│ │
Building A water entry Building B water entry
(house — factory plumbed, Mech. room shutoff → main floor
confirm connection point) bathroom, prep kitchen, fridge,
dishwasher, bar sink (via chase),
powder rooms ×2, outdoor kitchen,
hose bibs ×2
[all winterizable — indoor shutoffs]
[SEPTIC LEACH FIELD] ←── Caldwell Family Concrete (Invoice 2108)
│
│ 4" sewer lateral (shared trench, 1/4"/ft slope out)
├──────────────────────────────────────────────────────────
│ │
Building A sewer tie-in Building B sewer tie-in
(house — factory plumbed) Main floor: bathroom + prep kitchen
Upper floor: bar sink (via 5'5" chase),
powder rooms ×2
Exterior: outdoor kitchen drain
[all gravity-drainable for winterization]
SHARED TRENCH (one mobilization — Caldwell / 4K Services)
══════════════════════════════════════════════════════════════════
[ELEC CONDUIT]──[WATER LATERAL]──[SEWER LATERAL]──[WARNING TAPE]
│ │ │
to Bldg A to Bldg A to Bldg A
to Bldg B to Bldg B to Bldg B
to Leach Field
ROOF PENETRATIONS — Party Barn (Building B)
══════════════════════════════════════════════════════════════════
[C1-lower] [C1-upper] [Bath] [PR-1] [PR-2] [Hood] [C2-top]
Chimney 1 Chimney 1 Main Roost Roost Prep Chimney 2
main floor Roost fire floor PR-1 PR-2 kitchen (outdoor
firebox lounge exhaust exhaust exhaust exhaust top cap)
│
─────┴─────── dedicated ducts, no sharing (IMC 505)
[Outdoor kitchen hood] — separate penetration above Bldg A/B shared space
⚡ Electrical
Transformer → 200A split → Panel A-Main (house) + Panel B-Main (barn). Barn has Panel A (main floor, 42-space) and Panel B (Roost, 30-space) fed from Panel B-Main.
💧 Water
Well/Norwesco → 1" lateral → splits to Building A and Building B. All exterior lines (hose bibs, outdoor kitchen, outdoor fridge stub) have indoor shutoffs and pitched gravity drain for winterization with the back nine.
🚽 Sewer
Both buildings tie into shared 4" lateral → leach field. Outdoor kitchen drain also ties in. Caldwell Family Concrete executing septic + trenching in one mobilization.
Package E — Electrical
Service entrance, Panel A (main floor) + Panel B (The Roost), all branch circuits, lighting, devices, bay door openers, cart-charging infrastructure.
Package P — Plumbing
Water lateral, sewer lateral, vent, all fixtures and trim (both levels), water heater.
Package M — Mechanical (HVAC)
All three mini-split zones, line sets, condensate handling, exhaust fans.
Shared — Trenching / Excavation
Bid as one excavation scope (Caldwell/4K Services, already mobilized for septic) — not three separate trench mobilizations. Each trade prices conduit/pipe only, not trenching.
Open Item — Service Configuration
This document assumes the Party Barn's electrical service is a subpanel-style trunk feed off the house's main panel. The master-plan utility page describes a new dedicated transformer feeding the caretaker house and Party Barn on split 200A independent panels — i.e., two separate utility services. Confirm with the electrician and utility before ordering service equipment. It changes service-entrance materials but not the branch-circuit design in Panels A/B.
Recommended sequence: price shared trenching first (it gates all three trades), then bid E/P/M in parallel.
Loads in VA are estimated for sizing. A formal NEC Article 220 load calc should run once equipment cut-sheets are confirmed. Note: all lighting fixtures, low-voltage, AV, security, and CI integration are excluded from this schedule — Lumen Cache is handling full low-voltage and CI design separately. Circuits below cover power/HVAC/appliance scope only.
Low-Voltage, Lighting & CI — Lumen Cache Design Pending
All lighting fixture selection, low-voltage wiring, security system, AV integration, networking, access control, and smart-home/CI infrastructure is being designed by Lumen Cache in a dedicated design meeting. Everything in this build will be significantly more integrated and CI-forward than this initial MEP skeleton.
This panel schedule provides the home-run power circuits (breakers, wire gauge, panel positions) that the electrician needs to rough in. Lumen Cache will layer the full low-voltage design on top — fixture types, dimming topology, keypads, security zones, camera runs, WAP locations, AV racks, and control wiring. Do not treat the lighting rows below as fixture specs — they are rough-in power placeholders only.
| Ckt | Description | Zone | V | Breaker | Priority |
|---|---|---|---|---|---|
| A1 | Lighting — bay 1 (power rough-in; fixture spec: Lumen Cache) | Bay 1 | 120 | 20A/1P | Lumen Cache |
| A2 | Lighting — bay 2 (power rough-in; fixture spec: Lumen Cache) | Bay 2 | 120 | 20A/1P | Lumen Cache |
| A3 | Lighting — bay 3 (power rough-in; fixture spec: Lumen Cache) | Bay 3 | 120 | 20A/1P | Lumen Cache |
| A4 | Lighting — full bathroom (power rough-in; Lumen Cache) | Bathroom | 120 | 15A/1P | Lumen Cache |
| A5 | Lighting — prep kitchen (power rough-in; Lumen Cache) | Prep Kitchen | 120 | 15A/1P | Lumen Cache |
| A6 | Lighting — covered patio + ceiling fan(s) (power rough-in; Lumen Cache) | Patio | 120 | 15A/1P | Lumen Cache |
| A7 | Lighting — stairwell + landing, egress-rated (power rough-in; Lumen Cache) | Stair | 120 | 15A/1P | Lumen Cache |
| A8 | Lighting — exterior sconces, bay-door flanking (dark-sky; Lumen Cache) | Exterior | 120 | 20A/1P | Lumen Cache |
| A9 | Lighting — sign/branding (dark-sky, full-cutoff; Lumen Cache) | Exterior | 120 | 15A/1P | Lumen Cache |
| A10 | Lighting — string lights, deck/stair rail (Lumen Cache) | Exterior | 120 | 20A/1P | Lumen Cache |
| A11 | Security/safety — low ground-mounted exterior (no pole lights; Lumen Cache) | Exterior | 120 | 20A/1P | Lumen Cache |
| A12–A15 | Bay wall receptacles (4 circuits) | Bays 1–3 | 120 | 20A/1P | Core |
| A16 | Full bathroom receptacles (GFCI) | Bathroom | 120 | 20A/1P | Core |
| A17–A18 | Prep kitchen small-appliance circuits ×2 (GFCI) | Prep Kitchen | 120 | 20A/1P | Core |
| A19 | Covered patio GFCI receptacles | Patio | 120 | 20A/1P | Core |
| A20 | Dishwasher — prep kitchen (dedicated) | Prep Kitchen | 120 | 20A/1P | Core |
| A21 | Full refrigerator — prep kitchen (dedicated 20A) | Prep Kitchen | 120 | 20A/1P | Core |
| A21b | Double oven — prep kitchen (dedicated 240V — confirm 30A or 50A per unit spec) | Prep Kitchen | 240 | 50A/2P | Core |
| A21c | Range hood exhaust fan — dedicated duct straight out roof (independent termination, cannot share with bathroom exhaust per IMC 505) | Prep Kitchen | 120 | 20A/1P | Core |
| A22 | Electric water heater (point-of-use) | Mech. Room | 240 | 30A/2P | Core |
| A23 | Full bathroom exhaust fan — dedicated duct straight out roof | Bathroom | 120 | 15A/1P | Core |
| A24 | Mini-split — main-floor zone | Mech. Room | 240 | 20A/2P | Core |
| A25 | Air compressor — shop | Bay 2/3 | 240 | 30A/2P | Core |
| A26 | Welder receptacle NEMA 6-50R | Bay 3 | 240 | 50A/2P | Core |
| A27–A28 | Bay door openers ×2 | Bays | 120 | 20A/1P | Core |
| A29–A32 | Golf-cart charging (14 carts, 4 circuits) | Bays 1–2 | 120 | 20A/1P | Core |
| A33 | UTV/vehicle 240V charger NEMA 14-50 | Bay 3 | 240 | 50A/2P | Deferrable |
| A34 | Network rack, switch + WAPs | Elec. Rm | 120 | 20A/1P | Core |
| A35–A38 | Spare circuits (future expansion) | — | 120/240 | 20A | — |
| A39 | Outdoor kitchen — GFCI receptacles, outdoor-rated (shared Bldg A & B) | Outdoor Kitchen | 120 | 20A/1P | Core |
| A40 | Outdoor kitchen — dedicated appliance circuit (grill/griddle or outdoor range) | Outdoor Kitchen | 240 | 30A/2P | Core |
| A41 | Outdoor kitchen — refrigerator/kegerator (dedicated, outdoor-rated) | Outdoor Kitchen | 120 | 20A/1P | Core |
| A42 | Outdoor kitchen — hood/exhaust fan (dedicated duct straight out roof, independent termination) | Outdoor Kitchen | 120 | 20A/1P | Core |
| A43 | Outdoor kitchen — lighting (dark-sky compliant, full-cutoff) | Outdoor Kitchen | 120 | 20A/1P | Core |
| A44 | Main floor barn fireplace — circulation blower (Chimney 1, lower opening — wood-burning, no igniter) | Main Floor/Barn | 120 | 20A/1P | Core |
| A45 | Outdoor chimney Bldg A side — GFCI recept. + circulation blower (Chimney 2, lower — wood-burning, no igniter) | Outdoor/Bldg A | 120 | 20A/1P | Core |
| A46 | Outdoor chimney Bldg B side — GFCI recept. + lighting (Chimney 2, lower) | Outdoor/Bldg B | 120 | 20A/1P | Core |
| Ckt | Description | Zone | V | Breaker | Priority |
|---|---|---|---|---|---|
| B1 | Lighting — saloon general/accent (power rough-in; Lumen Cache) | Saloon | 120 | 20A/1P | Lumen Cache |
| B2 | Lighting — sim bay dedicated low-glare/dimming (power rough-in; Lumen Cache) | Saloon (sim) | 120 | 20A/1P | Lumen Cache |
| B3 | Lighting — bar island/bartender station (power rough-in; Lumen Cache) | Saloon (bar) | 120 | 15A/1P | Lumen Cache |
| B4 | Lighting — fire lounge (power rough-in; Lumen Cache) | Fire Lounge | 120 | 20A/1P | Lumen Cache |
| B5 | Lighting — game area (power rough-in; Lumen Cache) | Game Area | 120 | 20A/1P | Lumen Cache |
| B6 | Lighting — fitness zone + balcony (power rough-in; Lumen Cache) | Fitness/Balcony | 120 | 20A/1P | Lumen Cache |
| B7 | Lighting — indoor putting green accent/turf (Lumen Cache) | Putting Green | 120 | 15A/1P | Lumen Cache |
| B8 | Lighting — powder room 1 (power rough-in; Lumen Cache) | Powder Rm 1 | 120 | 15A/1P | Lumen Cache |
| B9 | Lighting — powder room 2 (power rough-in; Lumen Cache) | Powder Rm 2 | 120 | 15A/1P | Lumen Cache |
| B10 | Saloon — general receptacles | Saloon | 120 | 20A/1P | Core |
| B11 | Bar equipment circuit (kegerator/ice maker — dedicated GFCI) | Saloon (bar) | 120 | 20A/1P | Core |
| B12 | Golf-sim projector/PC/screen (dedicated clean power) | Saloon (sim) | 120 | 20A/1P | Core |
| B13 | AV/sound system — whole-Roost (Lumen Cache) | Saloon/AV nook | 120 | 20A/1P | Lumen Cache |
| B14 | Data/low-voltage — Cat6, network, control wiring (Lumen Cache) | Saloon | 120 | 20A/1P | Lumen Cache |
| B15 | Fire lounge — Roost fireplace circulation blower (Chimney 1, upper opening — wood-burning, no igniter) + receptacles | Fire Lounge | 120 | 20A/1P | Core |
| B15b | Exterior outdoor chimney — Roost deck level GFCI recept. + lighting (Chimney 2, upper) | Roost Deck/Exterior | 120 | 20A/1P | Core |
| B16 | Game area — receptacles | Game Area | 120 | 20A/1P | Core |
| B17 | Fitness zone — equipment receptacles (Peloton-rated) | Fitness/Balcony | 120 | 20A/1P | Core |
| B18 | Balcony — exterior GFCI receptacles | Balcony | 120 | 20A/1P | Core |
| B19 | Powder room 1 — GFCI recept. + exhaust fan | Powder Rm 1 | 120 | 20A/1P | Core |
| B20 | Powder room 2 — GFCI recept. + exhaust fan | Powder Rm 2 | 120 | 20A/1P | Core |
| B21 | Mini-split — Roost zone 1 (Saloon/sim/game area) | Saloon/Game | 240 | 30A/2P | Core |
| B22 | Mini-split — Roost zone 2 (fire lounge/fitness/balcony) | Fire/Fitness | 240 | 30A/2P | Core |
| B23 | Liquor storage — security/access control (Lumen Cache) | Saloon (bar) | 120 | 15A/1P | Lumen Cache |
| B24–B26 | Spare circuits (future bar/kitchen equipment) | — | 120/240 | 20A | — |
Winterization Design Standard — All Exterior & Outdoor Plumbing
At 8,040 ft with hard freeze/thaw cycles, every exterior and outdoor plumbing line is designed to drain completely — not just insulated. This is not freeze-proof-sillcock thinking; it is full seasonal shutdown. The outdoor kitchen, hose bibs, and any exterior sink are all configured so the water can be isolated at an indoor shutoff and the lines drained by gravity or blow-out before freeze season. Nothing outside depends on continuous heat tape to survive winter.
Tied to back nine winterization: The Turkey Toe winterization procedure for the back nine course plumbing (irrigation, drinking stations, wash areas) is done in one coordinated push — same crew, same compressor, same day. Party Barn exterior lines are added to that same winterization run so nothing gets missed and we're not making two trips.
Outdoor kitchen sink
Isolation valve inside + pitched drain line — gravity-drains fully when valve closed
Hose bibs (×2)
Full-port ball valve shutoff inside wall; lines pitch to bib for gravity drain — no standing water in line
Outdoor fridge/kegerator line
Flexible connection with indoor shutoff — disconnect and drain before freeze season
| Item / Spec | Location | Notes | Priority |
|---|---|---|---|
| Water lateral, 1" PEX/poly w/ heat-trace sleeve | Site → mech. room | Coordinate trenching with septic (Caldwell) for one mobilization | Core |
| Sewer lateral, 4" SDR-35 PVC + cleanouts | Mech. room → septic | Caldwell Family Concrete — min. 1/4"/ft slope | Core |
| Vent stack, main-floor fixture group | Roof penetration above bathroom | 2"–3" PVC, roof jack/flashing; serves bathroom + prep kitchen | Core |
| Vertical chase — Roost bar sink to main-level stack | Bar (upper) → main floor | 5'-5" chase; 1-1/2" drain, vent tie-in per plan set | Core |
| Toilet, 1.28 gpf, commercial-grade (×3) | Full bathroom + 2× powder rooms | 3" waste, 2" vent each | Core |
| Lavatory sink + faucet (×3) | Full bathroom + 2× powder rooms | 1-1/2" waste, vent each | Core |
| Shower/tub combo | Full bathroom | Rough-in is core; trim/surround is budget-flexible finish | Core |
| Prep kitchen sink + faucet | Prep kitchen | 1-1/2" waste, vent | Core |
| Prep kitchen full fridge — water line stub | Prep kitchen | 1/4" CW line + shutoff for fridge ice maker | Core |
| Dishwasher supply/drain | Prep kitchen | Dedicated supply + drain tie-in | Core |
| Range/oven — no plumbing (electric) | Prep kitchen | No gas — all-electric; plumbing scope is A21b circuit only | Core |
| Bar sink + faucet — bartender station | Saloon (bar) | 1/2" CW/HW; routes down 5'-5" chase above | Core |
| Icemaker line stub, 1/4" | Saloon (bar) | Small line, cheap to rough in with B11 | Core |
| Outdoor kitchen sink + faucet | Between Bldg A & B — exterior | CW/HW supply with indoor full-port ball valve shutoffs; line pitched to drain by gravity for seasonal winterization — part of back nine winterization run | Core |
| Outdoor kitchen drain | Between Bldg A & B — exterior | Drain to sewer lateral; pitched for full gravity drain when isolated | Core |
| Hose bibs (×2) — winterizable | Near bay ends | Full-port ball valve shutoff inside wall, line pitched to bib for complete gravity drain — no freeze-proof sillcock dependency; included in back nine winterization procedure | Core |
| Shop floor drain(s) + trap primer | Main floor wash-down | Confirm need with AHJ — omit if not required to simplify septic loading | Deferrable |
| Heat tape + pipe insulation | All exposed/interior runs | Interior lines: insurance layer at elevation. NOT a substitute for proper drain-down on exterior lines | Core |
| Equipment | Location | Capacity / Type | Power | Priority |
|---|---|---|---|---|
| Mini-split — main floor zone | Bathroom/prep kitchen | ~18,000 BTU, cold-climate ASHP, wall-mount head | 240V/20A (A24) | Core |
| Mini-split — Roost zone 1 | Saloon / sim / game area | ~36,000 BTU, cold-climate ASHP, ceiling cassette or wall-mount | 240V/30A (B21) | Core |
| Mini-split — Roost zone 2 | Fire lounge / fitness / balcony | ~36,000 BTU, cold-climate ASHP, wall-mount | 240V/30A (B22) | Core |
| Outdoor condensing units (×3) | Exterior — near mech. room/shop wall | Matched to indoor heads; ground pad or wall bracket | See elec. above | Core |
| Refrigerant line sets (×3) | Mech. room → each indoor head | Insulated copper, field-brazed or pre-charged | n/a | Core |
| Condensate drainage | Roost units primarily | Gravity drain to exterior; condensate pump if no fall | 120V if pump | Core |
| Full bathroom exhaust fan | Main floor bathroom | 80 CFM — dedicated duct straight out roof. Cannot share with range hood per IMC 505. | 120V (A23) | Core |
| Powder room exhaust fans (×2) | Upper level powder rooms | 50 CFM each — dedicated ducts straight out roof. Shortest vertical run from upper floor. | 120V (B19/B20) | Core |
| Range hood exhaust fan | Prep kitchen — main floor | Minimum 400 CFM, grease-rated duct — straight out roof, independent termination, grease cup at fan base. Cannot share duct with any bathroom exhaust per IMC 505. | 120V (A21c) | Core |
| Outdoor kitchen exhaust hood | Between Bldg A & B — exterior | Rated for outdoor use — dedicated duct straight out roof. Independent termination. | 120V (A42) | Core |
| General shop ventilation | Equipment/cart bays | Passive gable/ridge vent or powered wall exhaust | 120V if powered | Deferrable |
Mechanical Chase — Adjacent to Bathrooms, All Exhaust Out the Metal Roof
A dedicated mechanical chase is framed adjacent to the bathrooms on the main floor. All exhaust systems — bathroom, powder rooms ×2, range hood, and outdoor kitchen hood — run through or alongside this chase and terminate through the metal roof with pre-flashed standing-seam penetrations. Each system has its own dedicated duct and cap. No horizontal runs, no side wall penetrations, no shared ducts. The metal roof makes flashing straightforward and the grouped chase location keeps all roof penetrations clustered in one zone, away from the chimney stacks.
Roof penetration plan — all grouped in chase zone, metal roof with pre-flashed collars:
METAL ROOF — STANDING SEAM ┌──────────────────────────────────────────────────────────────────┐ │ │ │ CHIMNEY ZONE CHASE ZONE (adjacent to bathrooms) │ │ ┌──────────────┐ ┌────────────────────────────────┐ │ │ │ [C1-lower] │ │ [Bath] [PR-1] [PR-2] [Hood] │ │ │ │ Chimney 1 │ │ Main Roost Roost Prep │ │ │ │ main floor │ │ floor PR 1 PR 2 kitchen │ │ │ │ firebox flue │ │ exhaust exhaust exhaust exhaust │ │ │ │ │ │ │ │ │ │ [C1-upper] │ │ Each: dedicated duct, │ │ │ │ Chimney 1 │ │ back-draft damper, │ │ │ │ Roost fire │ │ insulated collar, │ │ │ │ lounge flue │ │ weatherproof cap │ │ │ └──────────────┘ │ Hood: grease-rated + UL cap │ │ │ └────────────────────────────────┘ │ │ │ │ OUTDOOR KITCHEN HOOD — separate penetration above A/B space │ │ [Outdoor hood] — own cap, own flue, pre-flashed standing seam │ │ │ │ CHIMNEY 2 (outdoor between Bldg A & B) — exterior masonry, │ │ not a roof penetration on the barn │ └──────────────────────────────────────────────────────────────────┘ IMC 505: range hood exhaust CANNOT share a duct with bathroom exhaust. All ducts above are independent. Chase provides physical separation and access for annual cleanout from the mechanical room side.
Bath exhaust
Main floor bathroom → chase → dedicated cap. 80 CFM minimum.
PR-1 + PR-2
Both Roost powder rooms → own ducts → own caps. 50 CFM each.
Range hood
Prep kitchen → grease-rated duct → grease cup at fan base → UL-listed grease cap. 400 CFM min. Independent of all bath ducts per IMC 505.
Outdoor kitchen
Separate roof penetration above the A/B shared space. Own rated cap.
▸ Chase location and duct routing to be confirmed on Eric's CDs before framing. Pre-flashed standing-seam collars ordered with roofing package — not field-cut after roofing is complete.
Wood-Burning Fireplaces — 2 Chimneys, 5 Fire Positions
Two chimneys, five places to sit around a fire. One chimney runs through the interior of the Party Barn serving both the main floor event space and The Roost fire lounge above it. One chimney sits outside between Building A and Building B — double-sided at the main floor so both buildings face it, and the same stack is accessible from the Roost deck on the second floor.
🪵 Chimney 1 — Interior Party Barn
Main Floor + The Roost · 2 Openings · 1 Flue
One chimney running through the barn interior. OPEN CODE QUESTION (Critical 2): one flue serving two separate fireboxes on two different floors may not be code-legal — each solid-fuel firebox typically needs its own flue. A see-through (single firebox, two openings at the same level) is the code-compliant alternative. Get mason or mechanical engineer confirmation before flat-pack fabrication. Do not assume this is resolved.
Main floor — barn interior
Event space / shop level. Firebox faces the gathering area.
The Roost — fire lounge
2nd floor. The anchor of the decompression zone.
🪵 Chimney 2 — Outdoor, Between Building A & B
Outdoor · Shared · 3 Seating Positions · 1 Flue
One outdoor masonry chimney positioned in the shared space between Buildings A and B. Double-sided firebox at the main floor — guests from both buildings can sit around it. The Roost deck on the 2nd floor also accesses the same chimney stack. OPEN STRUCTURAL QUESTION (Critical 1): a grease-rated hood duct and this chimney both require a roof to terminate through. There is currently no documented structure covering this space. A third structure — breezeway, pavilion, or covered outdoor room — appears to be needed. Design and CDs required before Caldwell trenches.
Building A side
Main floor — Caretaker Building faces the firebox
Building B side
Main floor — Party Barn faces the same firebox
Roost deck
2nd floor — upper deck off the same chimney stack
▸ AHJ approval required for chimney routing, flue sizing, cap, and spark arrestor. Masonry scope must be coordinated with structural flat-pack framing before framing is erected — chimney penetrations cannot be cut in after the fact.
Shared trenching
Electrical service/feed, water lateral, sewer lateral — one mobilization, coordinated with septic excavation (Caldwell).
Foundation/slab penetrations
Water, waste, vent, and electrical stub-ups before slab pour.
Flat-pack framing + mechanical chase — chimney locations locked
Panel A and Panel B locations confirmed. Mechanical chase framed adjacent to bathrooms with duct sleeves for all exhaust systems. Chimney 1 flue location locked in framing. Pre-flashed standing-seam collar locations communicated to roofing contractor. None of this can be cut in after framing is complete.
Framing complete in wet zones
Bathroom/prep kitchen (main floor) and Saloon/powder-room walls (Roost) must be framed before rough-in begins.
Rough-in — plumbing first, then electrical, then mechanical
Plumbing leads because waste/vent sizing constrains wall cavities electrical shares. Then conduit/boxes/wire, both panels. Then line sets, condensate, exhaust ducting.
Rough-in inspections
Electrical, plumbing, mechanical — all before insulation/drywall.
Insulation + drywall
Finished zones only: bathroom, prep kitchen, The Roost.
Trim-out
Plumbing fixtures set (bathroom, powder rooms, bar sink), electrical devices/fixtures installed on both panels, all three HVAC zones commissioned.
Exterior + Roost finish package
Dark-sky sconces, sign lighting, string lights, hose bibs, outdoor kitchen, condenser pads, bar equipment, sim/AV gear, fireplace trim — last, and first to cut if budget requires.
Startup / test
Both panels energized and labeled, water pressure/leak test, HVAC commissioning, chimney/fireplace inspection, final walk with all three trades.
If budget gets tight, Deferrable items throughout this document can move to a later phase without touching code-required rough-in. The rough-in for deferred fixtures/circuits stays — only the finish/equipment defers.
Nothing Tagged Core Should Defer
Core items get inspected, other trades build around them, or the space can't function without them — both panels/feeds, water/waste/vent rough-in, all three HVAC zones, life-safety/egress lighting, and the prep kitchen dishwasher connection.
Everything below is a real decision that affects scope, cost, or sequencing. Nothing here is speculative — each one needs a call before the relevant trade bids or mobilizes.
⚡ Electrical
Service configuration — trunk feed vs. independent transformer
The master-plan utility drawing shows a new transformer feeding Building A and Building B on split 200A independent panels (two separate utility services). This MEP assumes that, but confirm with the electrician and utility before ordering service equipment. Changes service-entrance materials; does not change Panel A or B branch circuits.
→ Electrician + utility — before service equipment order
Panel A slot count — 42-space may not be enough, recount before ordering
Circuit numbering has drifted (A21b, A21c, A39–A46). Every 240V/2-pole breaker consumes 2 slots: double oven (50A/2P), outdoor appliance (30A/2P), compressor (30A/2P), welder (50A/2P), water heater (30A/2P), UTV charger (50A/2P), mini-split (20A/2P), plus fireplace and outdoor chimney circuits. That's 14+ panel slots from 2-pole breakers alone, before single-pole circuits. A 60-space can may be needed. Have the electrician do a formal slot count before Panel A equipment is ordered.
→ Electrician — before panel equipment order
Double oven — 30A or 50A? And is there also a separate cooktop?
A21b is slotted at 50A/240V for headroom, but final breaker size depends on the unit. Most residential double ovens are 30A; commercial-grade units often require 50A. Separately: the zone table says 'range/oven' and the panel schedule says 'double oven.' A double wall oven has no cooktop. If there's also a range top, that's a separate dedicated 240V circuit not currently in Panel A. Decide: double wall oven only, or double oven + separate cooktop?
→ Appliance selection — before Panel A final schedule
AHJ + commercial kitchen code — NFPA 96, health dept, grease interceptor
A full fridge + double oven + 400 CFM grease hood is real cooking. Depending on jurisdiction and event/catering use, this may require: NFPA 96 fire suppression (Ansul system) over the hood, a grease interceptor on the kitchen sink and dishwasher drains (not just the wash-down bay floor drain), and a health department permit for event catering. This is an AHJ and health department conversation before kitchen scope is priced.
→ AHJ + health department — before kitchen scope is finalized
Occupancy classification — shop + event venue, AHJ ruling needed
A building that functions as equipment storage by day and an event venue by night may trigger different occupancy classification at use. This affects emergency lighting extent (main floor + Roost, not just the stairwell), exit signage requirements, occupant load calculation, and door hardware. Confirm with AHJ before electrical rough-in — egress lighting is locked in early.
→ AHJ — before electrical rough-in
Golf cart charger voltage
Plan assumes standard 120V on-board chargers (quad receptacles, A29–A32). If any carts need 240V fast-charge, circuits need to be upgraded. Confirm cart fleet spec.
→ Cart spec — low cost to change now, expensive after rough-in
🔧 Plumbing
Outdoor kitchen final location between A & B
Outdoor kitchen supply/drain lines need to be trenched alongside the main site utilities. The exact location between Building A and Building B needs to be locked on plan before Caldwell mobilizes for trenching — moving it after the trench is cut is expensive.
→ Caldwell trenching mobilization — lock before trench
Floor drain + grease interceptor — wash-down bay AND kitchen sink/dishwasher
Given the cooking equipment now in scope, the AHJ conversation needs to cover two things: (1) whether a floor drain/interceptor is required in the wash-down bay, and (2) whether a grease interceptor is required on the kitchen sink and dishwasher drain — standard for commercial-adjacent kitchens. Ask both in the same AHJ meeting. A grease interceptor on the kitchen drain is also tied to the NFPA 96 / commercial kitchen question (E4).
→ AHJ — before slab pour + before kitchen scope is finalized
Bar equipment list — kegerator, ice maker, etc.
B11 is sized for bar equipment, but the actual load and icemaker line size depends on what's going in the bar. Kegerator, undercounter ice maker, blender station? Each has different electrical and plumbing requirements. Lock the bar spec before Roost rough-in.
→ Bar design — before Roost rough-in
Burial method — conduit vs. direct-burial, PEX vs. poly
Conduit protects wire and allows future pulls but costs more to install. Direct-burial is cheaper but permanent. Same tradeoff for PEX vs. poly on the water lateral. AHJ may have a preference. Confirm before Caldwell trenches.
→ Caldwell trenching — confirm before mobilization
🌡️ Mechanical
Mini-split tonnage/models — all 3 zones
Sizes in this plan (18K BTU main floor, 36K BTU Roost zone 1, 36K BTU Roost zone 2) are estimates. An HVAC sub needs to run a Manual J heat load calc for the actual building at 8,040 ft before ordering equipment. Cold-climate-rated models are non-negotiable at this elevation.
→ HVAC sub — before equipment order; lead times can be 6–10 weeks
Shop ventilation — passive or powered?
Passive gable/ridge vents may be sufficient for general shop use. If the AHJ requires mechanical ventilation for compressor and welding fumes, a powered wall exhaust fan gets added to the scope. Ask AHJ before finalizing the mechanical scope.
→ AHJ ruling — low cost to add during framing, harder after
Mechanical chase — exact dimensions and location on plan
The chase is framed adjacent to bathrooms per this plan. Exact width, depth, and position need to appear on Eric's CDs before framing so the flat-pack fabrication accounts for it. This is a framing decision, not a finish decision.
→ Eric's CDs — before flat-pack fabrication (Huron Components)
Make-up air — 400 CFM hood likely triggers requirement
IMC 504.5 / IRC M1503.6 require mechanical make-up air when exhaust exceeds 400 CFM in most jurisdictions. Nothing in the current mechanical scope addresses make-up air. If required: dedicated make-up air duct, motorized damper, and possibly a tempering unit to pre-condition incoming air at 8,040 ft. Not a minor add — confirm with AHJ before mechanical scope is bid.
→ AHJ confirmation — before mechanical bid
🏗️ Structural & Design
Chimney 1 — one flue / two fireboxes: get engineer sign-off before fabrication
Described as one flue serving two fireboxes on two different floors. Solid-fuel fireplaces typically each require their own dedicated flue. The code-compliant version of a 'two-floor fire' is a see-through fireplace (one firebox, two openings at the same level). Two stacked fireboxes on separate floors sharing one flue is a different thing and needs mason/engineer confirmation. Cannot be corrected after flat-pack framing is erected.
→ Mason / mechanical engineer — before Huron fabricates flat-pack
Chimney 2 + outdoor kitchen hood — undocumented third structure needed
Both the outdoor kitchen grease hood duct and Chimney 2 require a roof to terminate through. Buildings A and B have no shared roof. There is no documented structure covering the outdoor A/B shared space. This appears to require a third structure — breezeway, pavilion, or covered outdoor room. That structure needs its own design, CDs, and foundation poured in Caldwell's site mobilization. This is a design gap, not a detail — it gates trenching.
→ Design + Eric's CDs — before Caldwell trenches
Welder amperage
A26 is slotted at 50A/240V (NEMA 6-50R). If you plan to run a smaller welder, 30A is sufficient and cheaper. If a plasma cutter or large MIG is planned, 50A is right. Pick your welder.
→ Low cost — just confirm before Panel A final schedule
Lumen Cache design meeting — schedule before framing, add universal rough-in fallback
All lighting fixture selection, dimming topology, security zones, camera locations, AV racks, control wiring, WAP placement, and access control is pending the Lumen Cache design session. If their design lags behind framing, add a universal rough-in standard to the framing spec now: extra empty conduit + pull string in all wall cavities and the chase. This is standard practice on CI-forward builds and prevents walls from being reopened later.
→ Schedule Lumen Cache meeting — before electrical rough-in. Add universal rough-in to framing spec regardless.
▸ Critical path: S1 (chimney engineer), S2 (third structure design), E4 (AHJ kitchen), M4 (make-up air) — these four must be resolved before Eric can finalize CDs. S2 also gates Caldwell trenching. S4 (Lumen Cache) must happen before electrical rough-in. M1 (HVAC tonnage) has 6–10 week lead time — start the sub conversation now.